The construction season is getting underway for 2023. Here are a few of the City’s upcoming projects as well as updates on others.
Please be mindful to slow down in construction zones to help keep workers and drivers safe this season.
Feel free to contact the City of Erlanger Public Works Department with comments or questions at info@erlangerpw.com or 859-72
Beaumont Homes LLC was awarded the contract for phase 2 of the Cahill Commons Park Project. This phase will see a new playground, a new half court basketball court, more seating wall and more fence. This project is slated to start in early fall of 2023.
The Debbie Ln, Jacqueline Dr, Kimberly Dr and Mitten Dr project is nearing completion. The contractor is slated to finish late August 2023.
Jefferson Construction was awarded a concrete street replacement on Circlewood Dr between Ridgewood Dr and Heartwood Ln and is slated to start in the middle of November 2023.
Riegler Blacktop was awarded a street resurfacing project on Summitridge Ln, Crestside Ct and Spire Cr, slated to start the week of September 4.
The City of Erlanger’s sidewalk replacement program will start in the fall of 2023 taking off where the contractor left off in 2022 in the Cherry Hill Subdivision.
SD1 is starting a sanitation/storm sewer project in the middle of August. This project is taking place on Sunset Ave, Lloyd Ave, Forest Ave and Fitzgerald Ct. Parts of this project will be in the street, front yards and backyards of the residences in that area. This is a SD1 project so if you have any questions, please call David Gilligan at 859-578-6775 or you can email him at dgilligan@sd1.org.