Public Works Monthly Report – March 2026

PROGRAMS

Pothole Patching

PW crews have been working in between the snow storms and rain events making rounds throughout the city patching potholes. So far a total of 357 potholes have been patched utilizing 31 Tons of hot mix asphalt material and 191 man hours.

Choke Points

The PW department has choke points throughout the city that are checked for debris before and after a substantial rainfall to prevent flooding issues. PW refers to these areas as the “Trashy Ten”. The Trashy Ten were checked Twice this month collecting trash and debris from around inlets to help prevent flooding.

Training

Four PW team members attended the Annual KLC Risk and Safety Conference March 3rd-6th. Four PW team members took their Pesticide Applicators test and passed. Two PW Team members are taking the CPSI (Certified Playground Safety Inspector) Course. The Certified Playground Safety Inspector (CPSI) certification program is the most comprehensive training program on playground hazard identification and risk management methods offered nationwide.

CAPITAL PROJECTS

Street Reconstruction Projects

The Deerchase Drive, Thorntree Drive, Brooke Court, and Whitetail Circle in the Deerchase subdivision and Skye Drive in the Sherbourne subdivision projects are slated to start the week of April 6th. These streets will be getting an asphalt overlay.

The Contractor has started on Locust Street, working first on the storm sewer upgrades followed by full depth repairs. Once those are done, they will install new curbs where needed and then a blacktop overlay.

The Narrows Road street and sidewalk project has begun with the Contractor doing the vegetation removal and then they will start the storm sewer upgrades.

Cintoya Drive will be getting a mill and overlay. The contract was awarded to Cincinnati Asphalt and they have slated mid May for a start date.

Concord Drive is slated to start the week of April 6th, with the Contractor doing full depth repairs, curb patching, and then a new layer of asphalt.

Sidewalk Replacement Program

The contractor that was awarded the sidewalk replacement project has started back in the Cherry Hill Subdivision. They have finished Mimosa and are currently working on Peach Tree Lane, moving their way toward Cypress Court.

Parks

Cincinnati Asphalt was awarded a project at Sherbourne Park to construct a new parking lot. The Contractor is slated to start in mid May with a completion date of mid June.

Silverlake Park is getting a new black 4-board horse fence, a new vinyl privacy fence, and a new black coated fence around the tennis courts. The contractor who was awarded the project is S&S Fence and they have a mid May start date.

Eons Dog Park

Electrical & Lighting: Installation is underway and expected to be completed by the end of March. Painting of the dog park and spine fence will follow.

Boulder Seat Wall: Construction has begun and is slated for completion by the end of March. Equipment & Facilities: Banner hardware has been delivered to the site. The bid opening for the maintenance building will take place on Thursday, March 26.

EONS Bike Park

Site Preparation: Earthwork is currently in progress. Paving and structural installation will immediately follow its completion.

Equipment: The container for the drop-in ramp has been delivered. Mural: Painting is scheduled to begin the week of March 30.

EONS Overlook

Cable Safety Railing: RFQs have been submitted, and a vendor selection is anticipated by the end of March.

Seat Wall: Boulders have been ordered. Site preparation will commence immediately following the completion of the dog park seat walls.

Timber & Swing: Materials have been delivered. Fabrication is expected to conclude by the end of April, with installation targeted for May.