Public Works Monthly Report – Jan 2026

PROGRAMS

2025 Trash Collection

One of PW’s many jobs is to pick up trash in the city parks, highway trash cans, and all the city’s right of ways, keeping Erlanger the cleanest city in the area. PW’s crews utilized 678 man hours picking up 940 bags of trash while driving 4173 miles throughout the city. The State of Kentucky has a grant program for picking up litter.

The City applies for a Litter Abatement Grant every year with the application being due November 1st, which applies to the next calendar year. During the year, records must be kept on how many man hours were used to pick up litter, how many bags of litter were picked up, and how many miles were driven to pick up litter. A report is then sent to the Division of Waste Management in Frankfort in

February outlining those details of that previous years Litter Program. The City received $ 9,215.28 for 2025 and we are awaiting the dollar amount to be released for the 2026 Grant.

Christmas Tree Recycling

The annual Christmas Tree recycling program was completed on January 13th, 2026. There were a total of 38 trees dropped off this year. The trees were mulched by the Kenton County Public Works and will be disbursed among several county parks as bedding and for walking paths.

Street Light Assessment

The PW’s department conducted it’s quarterly street light check. The quarterly street light check yielded 23 lights that needed attention. Five of these lights were reported to Duke Energy and the other 18 were reported to Owen Electric to have repaired.

Weather Warriors

The Weather Warriors were called into action for 1 weather event in January. This was for a measurable snowfall totaling about 10 inches. The crews utilized 319 tons of bulk salt at a cost of $ 28,082.00 and 429 man hours spread over 6 shifts.

CAPITAL PROJECTS

Street Reconstruction Projects

All street projects are on hold for the season and will resume in early spring.

There are a few upcoming projects that have been put out to bid. A small parking lot will be constructed for Sherbourne Park. Locust Street will get milled and repaved and Narrows Road will get new sidewalks and repaved.

Eons Adventure Park

The contractor installing the dog paddocks fence has ordered the supplies and will begin work once they receive them and the weather cooperates.

The contractor working on the Bike Pump Track and trails will begin work once the weather allows.